Sungun Copper Complex
230/63/20kV AIS Substation

Project Details

Location
Varzaqan, East Azerbaijan
End-User
Azerbaijan REC
Owner
NICICO
Azerbaijan Copper Complex
Consultant
Ghods Niroo Company
Awarded
Feb, 2019

Construction of 230/63/20 kV Substation Including:

  • 2 x Power Transformer 230/63kV, 80MVA
  • 2 x Power Transformer 230/20kV, 100MVA
  • 12 x Feeder 230kV
  • 7 x Feeder 63kV
  • 21 x Feeder 20kV
  • Control System: DCS
  • Awarded: Feb, 2019
  • Location: Varzaqan – East Azerbaijan

SSCO Company has been selected as the EPC Contractor for construction of 230/63/20kV AIS Substation in Order to Power up the New Sungun Copper Factory of Ore Harvesting, Preparation of concentrate, Melting and Condensation which is now under Construction by NICICO.

Photos


Get in Touch

+98 (21) 88 77 32 25
 
Fax