SSCO has been Short listed as the EPC Contractor for Construction of 400/63kV Kosar Substation in order to power up Safa Dasht, Alborz Province.
Construction of 400/63kV AIS Substation Including:
- 2 x Power Transformer 400/63kV, 200 MVA
- 2 x Feeder 400kV for input transmission line
- 2 x Feeder for 400kV Transformator
- 12 x Feeder for AIS 63kV Switchgear
- 400 and 63kV busbars
- 5 circuit breaker for busbars
- Ac/DC Panel Equipment
- Protection, PLC Panel
- Telecommunication Equipment etc.
- Control System: Conventional